Gulnar Park
All portfolio projects
CompletedInfrastructureClient: University of Lahore

Infrastructure · University of Lahore

Gulnar Park

Engineered civil works delivered to specification.

Status
Completed
Area / Scale
60,000 sq ft
Duration
18 Months
Start Date
October 2023
Completion
February 2025
Client
University of Lahore
Project Overview

Civil works for a campus park at the University of Lahore.

Gulnar Park at the University of Lahore was created through a civil works package delivered by LEHNAY GROUP. Levels were reshaped, pathways and hard landscaping were laid out, and drainage, irrigation routes and lighting infrastructure were installed to make the space usable as a daily campus amenity.

Civil works for a landscaped park, grading and level shaping, pathway and hard landscape construction, kerbs and edging, surface drainage, irrigation and lighting infrastructure, and seating and feature bases.

  • Reshaped levels and hard landscaping
  • Pathways with kerbs and edging
  • Drainage and irrigation infrastructure
  • Lighting and seating bases
Completed Project

Delivered, documented and handed over.

Completed & Handed Over

Status: Completed

Gulnar Park was completed, tested and handed over to the client in full.

Defects Liability Cleared

Post-handover

The maintenance period was served and all snag items closed out.

Records Available

Documentation

As-built drawings, test records and completion certificates are on file.

Share your details and the project team will respond with the full information pack.

Request Project Details
Scope packages

What this package covered

Earthworks & Formation

Site clearance, cut and fill, and compaction to formation level.

Pavement Works

Sub-base, base course and surfacing with kerbs and shoulders.

Wet Services

Sewerage, stormwater and potable water lines with chambers and testing.

Electrical Works

External electrification, transformers and street lighting.

Specifications

Technical details.

Civil Works
Civil Works
Concrete Grade
3000 psi for mass works, 4000 psi for structural members
Steel
Grade 60 deformed bars to ASTM A615
Testing
Cube, slump, compaction and pressure testing at every stage
Supervision
Full-time site engineer with stage-wise inspection records
Programme

Execution programme.

  1. October 2023

    Mobilisation

    Site establishment, survey, setting out and material approvals.

  2. Stage 1

    Substructure & Earthworks

    Excavation, foundations and formation-level works completed and tested.

  3. Stage 2

    Main Works

    Structure, pavement and primary civil works executed under stage inspection.

  4. Stage 3

    Services & Utilities

    Sewerage, water, electrical and mechanical services installed and tested.

  5. February 2025

    Finishing & Handover

    Finishes, snagging, testing and handover with as-built records.

Gallery

Work executed on site.

Location

University of Lahore

University of LahoreGet Directions
Hire us as your contractor

Tell us about the work you need done.

Share the basics of your own project and our contracts team will respond with a suggested approach, programme and budget estimate.

LEHNAY GROUP
Engineering integrity. Delivered on time.

Our teams execute civil, structural, MEP and finishing scopes for private developers, institutions and public clients across housing, education, healthcare, religious, commercial, industrial and infrastructure sectors.

University of Lahore
Infrastructure