Main Stage
All portfolio projects
CompletedInfrastructureClient: University of Lahore

Infrastructure · University of Lahore

Main Stage

Engineered civil works delivered to specification.

Status
Completed
Area / Scale
30,000 sq ft
Duration
18 Months
Start Date
October 2018
Completion
November 2019
Client
University of Lahore
Project Overview

A permanent event stage for the University of Lahore.

The Main Stage at the University of Lahore is a permanent performance structure built by LEHNAY GROUP. The platform and its backdrop frame were engineered for stage rigging, lighting and sound loads, with cable routes and power provision built into the structure rather than added afterwards.

Structure and civil works for a permanent stage, RCC platform and foundations, backdrop and rigging frame designed for equipment loads, integrated cable routes and power provision, access steps and ramps, and surrounding paved areas.

  • Platform engineered for rigging and equipment loads
  • Cable routes and power built into the structure
  • Access steps and ramp provision
  • Paved surrounding assembly area
Completed Project

Delivered, documented and handed over.

Completed & Handed Over

Status: Completed

Main Stage was completed, tested and handed over to the client in full.

Defects Liability Cleared

Post-handover

The maintenance period was served and all snag items closed out.

Records Available

Documentation

As-built drawings, test records and completion certificates are on file.

Share your details and the project team will respond with the full information pack.

Request Project Details
Scope packages

What this package covered

Earthworks & Formation

Site clearance, cut and fill, and compaction to formation level.

Pavement Works

Sub-base, base course and surfacing with kerbs and shoulders.

Wet Services

Sewerage, stormwater and potable water lines with chambers and testing.

Electrical Works

External electrification, transformers and street lighting.

Specifications

Technical details.

Civil Works
Structure & Civil Works
Concrete Grade
3000 psi for mass works, 4000 psi for structural members
Steel
Grade 60 deformed bars to ASTM A615
Testing
Cube, slump, compaction and pressure testing at every stage
Supervision
Full-time site engineer with stage-wise inspection records
Programme

Execution programme.

  1. October 2018

    Mobilisation

    Site establishment, survey, setting out and material approvals.

  2. Stage 1

    Substructure & Earthworks

    Excavation, foundations and formation-level works completed and tested.

  3. Stage 2

    Main Works

    Structure, pavement and primary civil works executed under stage inspection.

  4. Stage 3

    Services & Utilities

    Sewerage, water, electrical and mechanical services installed and tested.

  5. November 2019

    Finishing & Handover

    Finishes, snagging, testing and handover with as-built records.

Gallery

Work executed on site.

Location

University of Lahore

University of LahoreGet Directions
Hire us as your contractor

Tell us about the work you need done.

Share the basics of your own project and our contracts team will respond with a suggested approach, programme and budget estimate.

LEHNAY GROUP
Engineering integrity. Delivered on time.

Our teams execute civil, structural, MEP and finishing scopes for private developers, institutions and public clients across housing, education, healthcare, religious, commercial, industrial and infrastructure sectors.