LEHNAY.
Allied Health Sciences Department
All portfolio projects
CompletedEducationalClient: University of Lahore

Educational · University of Lahore

Allied Health Sciences Department

A purpose-built campus designed around teaching.

Status
Completed
Area / Scale
30,000 sq ft
Duration
30 Months
Start Date
March 2019
Completion
July 2020
Client
University of Lahore
Project Overview

A teaching and laboratory block for allied health sciences.

The Allied Health Sciences Department at the University of Lahore was built by LEHNAY GROUP from structure through to final finish. The building houses teaching laboratories, demonstration rooms and faculty offices, with services planned around laboratory requirements, fume extraction routes, laboratory drainage and heavier power provision than a standard academic block.

Structure, gray and finishing works for an academic and laboratory building, RCC frame, masonry and plaster, chemical-resistant laboratory finishes, laboratory drainage and extraction provisions, electrical and data distribution, joinery and sanitary blocks.

  • Teaching laboratories with specialist services
  • Chemical-resistant laboratory finishes
  • Laboratory drainage and extraction routes
  • Faculty offices and demonstration rooms
Completed Project

Delivered, documented and handed over.

Completed & Handed Over

Status: Completed

Allied Health Sciences Department was completed, tested and handed over to the client in full.

Defects Liability Cleared

Post-handover

The maintenance period was served and all snag items closed out.

Records Available

Documentation

As-built drawings, test records and completion certificates are on file.

Share your details and the project team will respond with the full information pack.

Request Project Details
Academic spaces

What the campus contains

Classrooms

Naturally lit teaching spaces with cross ventilation and smart-board provision.

Science Laboratories

Physics, chemistry and biology labs with service benches and safety fittings.

Computer Lab & Library

Networked computer lab and a reading library on the upper floor.

Activity & Sports Areas

Assembly hall, activity room and an open play area.

Specifications

Technical details.

Structure
RCC frame with brick masonry infill
Classrooms
28 teaching spaces with cross ventilation
Laboratories
Physics, chemistry, biology and computer labs
Circulation
Double-loaded corridors with two protected staircases
Safety
Fire extinguishers, alarm points and CCTV coverage
Programme

Execution programme.

  1. March 2019

    Mobilisation

    Site establishment, survey, setting out and material approvals.

  2. Stage 1

    Substructure & Earthworks

    Excavation, foundations and formation-level works completed and tested.

  3. Stage 2

    Main Works

    Structure, pavement and primary civil works executed under stage inspection.

  4. Stage 3

    Services & Utilities

    Sewerage, water, electrical and mechanical services installed and tested.

  5. July 2020

    Finishing & Handover

    Finishes, snagging, testing and handover with as-built records.

Gallery

Work executed on site.

Location

University of Lahore

University of LahoreGet Directions
Hire us as your contractor

Tell us about the work you need done.

Share the basics of your own project and our contracts team will respond with a suggested approach, programme and budget estimate.

LEHNAY GROUP
Engineering integrity. Delivered on time.

Our teams execute civil, structural, MEP and finishing scopes for private developers, institutions and public clients across housing, education, healthcare, religious, commercial, industrial and infrastructure sectors.

University of Lahore
Educational