LEHNAY.
SOCA Building
All portfolio projects
CompletedEducationalClient: University of Lahore

Educational · University of Lahore

SOCA Building

A purpose-built campus designed around teaching.

Status
Completed
Area / Scale
30,000 sq ft
Duration
10 Months
Start Date
August 2012
Completion
July 2014
Client
University of Lahore
Project Overview

Finishing works for the SOCA building.

LEHNAY GROUP executed the finishing package for the SOCA building at the University of Lahore. Working after the structure was in place, the team delivered plaster, flooring, painting, joinery and service terminations to a level of finish appropriate to a public-facing academic building on a busy campus.

Finishing works package, plaster and skim, floor and wall finishes, painting systems, timber and aluminium joinery, false ceilings, sanitary fit-out and electrical and mechanical terminations, delivered on an occupied campus with controlled access and clean-up.

  • Complete architectural finishing package
  • False ceilings and service terminations
  • Public-facing quality of finish
  • Executed on an occupied campus
Completed Project

Delivered, documented and handed over.

Completed & Handed Over

Status: Completed

SOCA Building was completed, tested and handed over to the client in full.

Defects Liability Cleared

Post-handover

The maintenance period was served and all snag items closed out.

Records Available

Documentation

As-built drawings, test records and completion certificates are on file.

Share your details and the project team will respond with the full information pack.

Request Project Details
Academic spaces

What the campus contains

Classrooms

Naturally lit teaching spaces with cross ventilation and smart-board provision.

Science Laboratories

Physics, chemistry and biology labs with service benches and safety fittings.

Computer Lab & Library

Networked computer lab and a reading library on the upper floor.

Activity & Sports Areas

Assembly hall, activity room and an open play area.

Specifications

Technical details.

Structure
RCC frame with brick masonry infill
Classrooms
32 teaching spaces with cross ventilation
Laboratories
Physics, chemistry, biology and computer labs
Circulation
Double-loaded corridors with two protected staircases
Safety
Fire extinguishers, alarm points and CCTV coverage
Programme

Execution programme.

  1. August 2012

    Mobilisation

    Site establishment, survey, setting out and material approvals.

  2. Stage 1

    Substructure & Earthworks

    Excavation, foundations and formation-level works completed and tested.

  3. Stage 2

    Main Works

    Structure, pavement and primary civil works executed under stage inspection.

  4. Stage 3

    Services & Utilities

    Sewerage, water, electrical and mechanical services installed and tested.

  5. July 2014

    Finishing & Handover

    Finishes, snagging, testing and handover with as-built records.

Gallery

Work executed on site.

Location

University of Lahore

University of LahoreGet Directions
Hire us as your contractor

Tell us about the work you need done.

Share the basics of your own project and our contracts team will respond with a suggested approach, programme and budget estimate.

LEHNAY GROUP
Engineering integrity. Delivered on time.

Our teams execute civil, structural, MEP and finishing scopes for private developers, institutions and public clients across housing, education, healthcare, religious, commercial, industrial and infrastructure sectors.

University of Lahore
Educational