CompletedReligiousClient: University of Lahore

Religious · University of Lahore

Jamia Masjid – University of Lahore

A place of worship built to last generations.

Status
Completed
Area / Scale
24,000 sq ft
Duration
12 Months
Start Date
April 2019
Completion
December 2020
Client
University of Lahore
Project Overview

The front elevation structure of the campus masjid.

At the University of Lahore, LEHNAY GROUP executed the front elevation structure of the campus Jamia Masjid, the arched facade, minaret elements and entrance portal that give the building its identity across the campus. The work required precise geometry and formwork to reproduce the architect's profiles faithfully.

Construction of the masjid's front elevation structure, RCC and masonry elements, arch and portal formwork, minaret components, cladding substrate and finishing interfaces, executed to tight geometric tolerances on an operational campus.

  • Architectural arch and portal geometry
  • Purpose-built formwork for curved profiles
  • Minaret elements and cladding substrate
  • Executed on an operational campus
Completed Project

Delivered, documented and handed over.

Completed & Handed Over

Status: Completed

Jamia Masjid was completed, tested and handed over to the client in full.

Defects Liability Cleared

Post-handover

The maintenance period was served and all snag items closed out.

Records Available

Documentation

As-built drawings, test records and completion certificates are on file.

Share your details and the project team will respond with the full information pack.

Request Project Details
Spaces

What the masjid contains

Main Prayer Hall

Column-optimised hall with marble flooring and clear sight lines to the mehrab.

Mehrab & Minbar

Finished in marble with recessed lighting and integrated sound.

Wudu & Washrooms

Separate wudu area with washrooms and drainage.

Courtyard

Shaded open courtyard used for overflow congregation on Fridays.

Specifications

Technical details.

Structure
RCC frame with load-bearing masonry and RCC dome
Prayer Capacity
Approximately 900 worshippers
Minarets
2 minaret(s) in matching finish
Finishes
Marble flooring, plastered and painted internal surfaces
Services
Wudu area, washrooms, sound system and ceiling fans
Programme

Execution programme.

  1. April 2019

    Mobilisation

    Site establishment, survey, setting out and material approvals.

  2. Stage 1

    Substructure & Earthworks

    Excavation, foundations and formation-level works completed and tested.

  3. Stage 2

    Main Works

    Structure, pavement and primary civil works executed under stage inspection.

  4. Stage 3

    Services & Utilities

    Sewerage, water, electrical and mechanical services installed and tested.

  5. December 2020

    Finishing & Handover

    Finishes, snagging, testing and handover with as-built records.

Gallery

Work executed on site.

Location

University of Lahore

University of LahoreGet Directions
Hire us as your contractor

Tell us about the work you need done.

Share the basics of your own project and our contracts team will respond with a suggested approach, programme and budget estimate.

LEHNAY GROUP
Engineering integrity. Delivered on time.

Our teams execute civil, structural, MEP and finishing scopes for private developers, institutions and public clients across housing, education, healthcare, religious, commercial, industrial and infrastructure sectors.

University of Lahore
Religious